Construction records and billing

Subcontractor Change Orders: Free Log and Approval Guide

Keep scope, price, time and authority traceable from the first request through invoice review.

By SubDoc Editorial Team · Published September 30, 2026 · Updated October 30, 2026

Download a subcontractor change order log

Track subcontractor changes in one register, with proposed amounts separate from executed adjustments. Link each row to the request, supporting records, decision and applicable billing instruction. Update the authorized contract value from the executed adjustments recorded under your agreement, while keeping unresolved exposure visible in a separate total.

These original CSV files open in common spreadsheet applications. They contain no macros, automatic calculations or legal terms. No email or account is needed:

The register is an administrative tool. It does not authorize work, amend an agreement, create a payment right or replace the change document your subcontract requires. Keep the actual signed records in your project file.

Request, change order and directive: record the difference

A proposed change is not necessarily an agreed change. Record what each document actually does under your subcontract instead of treating every document titled “CO” as interchangeable.

Suggested register classifications; your contract controls their effect
RecordWhat to captureReview question
Potential change or requestScope issue, estimate, supporting reference and submitted dateHas anyone agreed to the price, time or authority to proceed?
Executed change orderSigned document, agreed adjustment and effective referenceDo the register and signed terms match?
Directive with unresolved pricingWritten direction, authorized issuer, cost-record method and unresolved itemsWhat does the subcontract require while price or time is being determined?
Rejected or withdrawn requestDecision reference and date, with earlier records retainedDoes another instruction or dispute still need an owner?

AIA's G701S instructions describe a particular contractor–subcontractor change document covering agreed changes in scope, sum and time, with both parties' signatures. Its requirements do not establish the procedure for every subcontract. Use your required form; the CSV here does not reproduce an AIA document.

The AGC, ASA and ASC project guidelines, section D.3.d, distinguish negotiated changes, time-and-material arrangements and directives where adjustments are not yet agreed. They emphasize written authorization and defining reimbursable costs. Read the actual agreement before assuming work must stop or that every pending amount is unbillable.

What belongs in the log?

Use one row for each change reference on a specific subcontract. Give revisions their own identifiers so an old quote is not mistaken for the current proposal. The downloads include these field groups:

  • Identity: project, subcontractor legal name, subcontract reference, request number and revision.
  • Basis: short scope description, originating RFI or direction, and evidence location.
  • Money: requested adjustment and executed adjustment in separate columns, including negative amounts for deductions.
  • Time: requested and agreed schedule adjustments, with a separate schedule-review reference.
  • Authority: status, issuer or reviewer, executed date and signed-document reference.
  • Follow-through: related owner-side change, billing instruction, next action, action owner and next review date.

These are suggested operational fields rather than a nationwide legal checklist. Choose status names your team can apply consistently. “Approved for pricing review” and “executed” should not collapse into one ambiguous “approved” label.

Retain a deductive change even when its amount is small. A negative adjustment must remain visible in the signed record, register and reconciliation. If the subcontractor and GC disagree about the deduction, record the dispute rather than entering an agreed credit that does not exist.

A practical review workflow from field issue to accounting

  1. Capture the issue promptly. Identify the changed work and source reference. Preserve relevant instructions, drawings, photos and dated field records. Follow your subcontract's notice procedure and route deadlines for qualified review; an entry in this spreadsheet is not contractual notice.
  2. Confirm who can give direction. Identify the person with authority under the agreement. Record the written instruction and whether the work is being priced, directed or agreed. A field conversation alone leaves important questions unanswered.
  3. Review scope, cost and time together. Identify inclusions, exclusions, quantities and supporting rates where applicable. Record schedule impact separately; do not assume a requested extension was granted because a price was accepted.
  4. Record the actual decision. Attach the executed document or decision reference and preserve earlier revisions. For an unresolved directive, retain its separate status and the required cost records instead of marking it executed.
  5. Hand off a checked packet. Give accounting the agreed reference, adjustment, billing instruction and document location. Ask the recipient to confirm the version used in its contract register.

Owner-side recovery needs its own tracking. Cross-reference an upstream change where relevant, but do not assume owner approval settles the subcontractor's entitlement or that a subcontract change guarantees recovery from the owner. Have the responsible contract reviewer address each agreement.

The ABA's change-order overview explains that standard contract processes can permit directed work before price and time are agreed. The named forms have different mechanisms. That is why the log preserves the direction and open questions instead of imposing a universal “never bill pending work” rule.

Worked example: additions, deductions and pending exposure

Consider a fictional electrical subcontract with an original value of $120,000. The example download contains four changes. These are invented figures for reconciliation practice, not customer results or recommended prices.

Fictional changes for Demo Project C
ReferenceStatusRequested adjustmentExecuted adjustment
CO-01: additional lightingExecuted$8,500$8,500
CO-02: removed fixturesExecuted−$3,000−$3,000
PCO-03: revised routingPricing review$6,200Not agreed
PCO-04: duplicate requestWithdrawn$900Not agreed

The executed adjustments total $5,500: $8,500 − $3,000. The register's executed contract value is therefore $125,500. The $6,200 under review stays in the pending-exposure column; the withdrawn $900 is excluded from that total. This separation describes register reporting, not a decision about contractual entitlement.

Suppose earlier gross billings total $90,000 and the next current-period invoice requests $40,000 on the same basis. Combined gross billing would be $130,000, which is $4,500 above the executed value. Flag it for reconciliation. Check whether a missing executed change, a duplicate line, an agreed billing mechanism or another adjustment explains the difference.

Do not declare that the entire invoice is invalid or automatically withhold it. Follow the contract, applicable law and authorized review process for disputed amounts, notices and undisputed payment. This example excludes retainage, tax and other adjustments to keep the arithmetic visible. A billing balance also does not prove how much physical work remains.

The example file keeps requested and agreed days separate. Do not add days mechanically to a completion date: overlapping changes and the agreed schedule method may require further review. A blank agreed-days cell means unresolved, while a recorded zero means the executed document grants no adjustment in this example.

Check each invoice against the same version of the contract

Use the subcontractor invoice approval workflow to route the bill. First confirm whether it is a current-period invoice or a cumulative application; the payment application versus invoice guide explains that distinction. Mixing current charges with cumulative totals can double-count earlier work.

Match each changed-work line to its reference and actual billing instruction. Compare amounts on the same basis, preserving tax, retainage, prior billings and payments as separate items where the required format calls for them. Use the subcontractor invoice template for a simple itemized request when appropriate; it is not a substitute for a required progress application.

At final reconciliation, account for every open request, direction, deduction and revision. Record what remains disputed and who owns the next step. Ask the contract administrator how unresolved items must be handled before signing a final account or release. A clean spreadsheet does not itself settle rights.

A ten-minute register review for the project team

Use a short recurring review as an administrative habit; ten minutes is a suggested meeting length, not a measured productivity result. Filter for entries missing an action owner, next review date, evidence reference or clear status. Discuss what must happen next and record the answer on the row.

  • Does accounting have every newly executed adjustment, including deductions?
  • Is any request still assigned to a person who has left the project?
  • Do field records reference an instruction absent from the register?
  • Does a revised quote still appear beside an earlier version without a superseded label?
  • Are any contractual notice or response requirements waiting for qualified review?

Export a dated review copy under your approved records process and retain the underlying documents. For electronic agreement handling, see the subcontractor e-signing guide. This article makes no claim that SubDoc drafts changes, determines entitlement or automatically authorizes payments.

Common questions

Can I use the CSV in Excel or Google Sheets?

Yes. Import it as a comma-separated file and check that dates and amounts are interpreted correctly. The downloads are plain data: add your own reviewed formulas if needed. Clear the fictional example before using it for a real project.

Should a pending request change the executed contract total?

Keep it separate in this register until the applicable adjustment is executed. Preserve directed-work and billing instructions separately; the reporting label does not determine what your agreement permits or requires.

Who signs a subcontractor change order?

Use the parties and authorized signatories required by your agreement. Confirm their authority instead of assuming a job title or email approval is enough. AIA's G701S is one specific contractor–subcontractor document; your form may differ.

Download the blank log and use the filled example to test your reconciliation before entering live project records.

This content is general information, not legal, insurance, or professional advice. Insurance and contract requirements vary by state, project, and policy. Consult a licensed attorney or insurance professional before relying on it.