How to Request a Certificate of Insurance from a Subcontractor

Most certificates come back wrong because the request was vague. "Please send us your COI" gets you whatever the agent sent the last general contractor. Here's what a complete request includes, who to send it to, and three email templates you can copy for new, corrected and renewal certificates.

Direct Answer

To request a certificate of insurance from a subcontractor, send a written request at contract award to the sub and their insurance agent. It should list your exact legal name for the certificate holder box, the coverages and limits your subcontract requires, the endorsements you need (additional insured, waiver of subrogation, primary and non-contributory, notice of cancellation), the project reference, and a deadline before mobilization. Ask for the endorsement pages, not just checked boxes.

1. When to Request a Certificate

A certificate request isn't a one-time onboarding step. You'll send one at four points in a subcontractor relationship:

At award

Before the subcontract is signed or immediately after. Requirements that force a policy change (a new endorsement, a higher limit) need lead time.

Before mobilization

Enforce "no certificate, no site access". It's the last point where you have full leverage.

Before each renewal

30 or more days before the expiration date on file. Most lapses happen at renewal, not mid-term.

When scope changes

New project, new owner to name as additional insured, or a scope that needs higher limits or an umbrella.

2. What to Include in a COI Request

Your request should read like a spec sheet. Every line below maps to a box or endorsement on the ACORD 25, so the agent can fill it in without a follow-up call. Pull the limits from your subcontract. If you haven't set them yet, our subcontractor insurance requirements by trade guide has typical ranges.

ItemWhat to writeWhy it matters
Certificate holderYour exact legal entity name and mailing address, e.g. "ABC Builders LLC, 100 Main St, Austin, TX 78701"A DBA or shorthand name is the #1 reason certificates get re-issued.
Additional insuredWho must be named (you, the owner, others the prime contract requires), for ongoing AND completed operations, e.g. ISO CG 20 10 + CG 20 37 or equivalentCompleted-operations coverage protects you after the sub leaves the job.
Coverages & limitsThe exact minimums from your subcontract for General Liability, Auto, Workers' Comp / Employer's Liability and UmbrellaAgents can't guess. They'll send whatever the policy already shows.
Waiver of subrogationWhich lines it's required on (commonly GL, Auto and WC)Stops the sub's carrier from suing you to recover a claim it paid.
Primary & non-contributory"Coverage for the additional insureds is primary and non-contributory"Makes the sub's policy pay before yours.
Notice of cancellation30 days' written notice of cancellation to the certificate holder, by endorsementThe ACORD 25 box alone doesn't create a notice obligation.
Project referenceProject name, address and job number for the Description of Operations boxTies the certificate (and any project-specific endorsement) to your job.
DeadlineA date before mobilization, and where to send itNo certificate, no site access. Say it up front.

If the difference between the additional insured and waiver of subrogation lines is fuzzy, see primary and non-contributory vs. waiver of subrogation, and for why notice of cancellation needs an endorsement, see what a notice of cancellation is.

3. Copy-Paste COI Request Email Templates

Replace everything in [brackets]. Keep the endorsement list even if the sub says "my agent knows what you need", because the written list is what you'll point to when a certificate comes back incomplete.

Template 1: Initial COI request

Send at award, to the sub and their insurance agent.

Subject: Certificate of insurance required: [Project Name] / [Subcontractor Name]

Hi [Name],

Before [Subcontractor Name] can mobilize on [Project Name] ([Project Address]), we need a current certificate of insurance plus endorsements that meet the requirements below. Please forward this to your insurance agent, or reply with their email and we'll send it directly.

Certificate holder:
[Your Company Legal Name]
[Street Address, City, State ZIP]

Additional insured (ongoing AND completed operations, e.g. CG 20 10 + CG 20 37 or equivalent):
[Your Company Legal Name], [Owner Name], and their officers and employees

Minimum coverage:
- General Liability: $[1,000,000] each occurrence / $[2,000,000] aggregate
- Auto Liability: $[1,000,000] combined single limit
- Workers' Comp: statutory; Employer's Liability $[1,000,000]
- Umbrella/Excess: $[X] (if required)

Required endorsements (please attach the endorsement pages):
- Additional insured (GL, and Auto if required)
- Waiver of subrogation (GL, Auto, WC)
- Primary and non-contributory (GL)
- 30-day notice of cancellation to the certificate holder

Description of operations: [Project Name], [Job #], [Project Address]

Please send by [Date]. Work can't start until we have a compliant certificate on file.

Thank you,
[Your Name] | [Title] | [Phone]

Template 2: Deficiency / correction request

Send to the agent when a certificate comes back wrong. Be specific.

Subject: Correction needed: COI for [Subcontractor Name] / [Project Name]

Hi [Agent Name],

Thanks for the certificate dated [Date]. It doesn't meet the subcontract requirements yet. Could you re-issue it with the following changes?

1. Certificate holder should read: [Exact Legal Name, Address]
2. [Example: General Liability aggregate must be at least $2,000,000; certificate shows $1,000,000]
3. [Example: Please attach the CG 20 37 completed operations additional insured endorsement]
4. [Example: Waiver of subrogation is required on the Workers' Comp policy]

Everything else on the certificate looks good. [Subcontractor Name] is scheduled to start on [Date], so a corrected certificate by [Date] would keep them on schedule.

Thank you,
[Your Name] | [Title] | [Phone]

Template 3: Renewal request

Send 30+ days before the policy expiration date on file.

Subject: Renewal certificate needed: [Subcontractor Name] policies expire [Expiration Date]

Hi [Name],

Our records show [Subcontractor Name]'s [General Liability / Workers' Comp / Auto] policy expires on [Expiration Date]. To keep [Subcontractor Name] active on [Project Name], please send an updated certificate showing the renewed policy term, with the same certificate holder, additional insured and waiver of subrogation requirements as the current certificate.

If the carrier or policy number is changing at renewal, please include the new endorsement pages as well.

Please send by [Date, at least 7 days before expiration].

Thank you,
[Your Name] | [Title] | [Phone]

4. Send It to the Agent, Not Just the Subcontractor

A subcontractor usually can't change what their certificate says. Only their insurance agent can. Routing the request through the sub adds a relay step and a chance for the request to get summarized into "they want a COI". Sending it to the agent directly (copying the sub) has three advantages:

  • Accuracy: the agent sees your exact requirements and can flag anything the policy doesn't cover yet.
  • Endorsements: the agent can attach the actual endorsement forms in the same reply.
  • Authenticity: a certificate that comes straight from the agency is far harder to alter. See how to spot a fake certificate of insurance.

Ask for the agent's contact in your subcontractor onboarding form so you have it before the first request goes out.

5. Why Certificates Come Back Wrong (and How to Prevent It)

Certificate holder name or address is wrong. Give the exact legal name and address in writing, and never just a company nickname.

Additional insured box checked, no endorsement. Ask for the endorsement pages by name (e.g. CG 20 10 and CG 20 37 or equivalent).

Limits below your minimums. State each limit in the request so the agent can tell the sub before they send it that the policy needs to change.

Policy expires during the project. Ask for the renewal certificate 30+ days out and track the new expiration date.

The insured isn't the entity you contracted with. Match the named insured to the legal name on your subcontract.

Before approving what comes back, run it through the ACORD 25 inspection checklist. If you're still logging certificates by hand, the free COI tracking spreadsheet template has columns for every requirement above.

6. Automating COI Requests and Renewals

Templates work for a handful of subs. Past that, the time goes into tracking who replied, what was wrong, and whose policy renews next month. That's the part worth automating. For the broader system, see our guide to tracking certificates of insurance.

How SubDoc handles the request

SubDoc emails each subcontractor a passwordless upload link, and the sub can forward it to their broker in one click. When the certificate comes back, AI reads the ACORD 25 and checks limits, dates and endorsements against your requirements, so your review starts from a list of what's missing. Your team is alerted before each policy expires, and one click sends the sub a renewal request with the same upload link. It's free for vendors, and free for up to 3 vendors on your side.

Frequently Asked Questions

Send a written request (email is fine) to the subcontractor and, ideally, directly to their insurance agent. Include your exact legal name and address for the certificate holder box, the coverages and limits your subcontract requires, any required endorsements (additional insured, waiver of subrogation, primary and non-contributory, notice of cancellation), the project name and address, and a deadline before mobilization. Ask for the endorsement pages to be attached, not just checked on the certificate.